PROJECT SUMMARY
Name of Project
Construction of Two Laning with Hard Shoulder of Tara - Premnagar - Ramanujnagar Road Section fromExisting Chanaige Km 0.000 to Km 50.312 (Design Chainage from Km 0.000 to Km 50.242) in the State of Chhattisgarh on EPC Mode. Length : 50.242 Km Name of District: Surajpur. Vidhansabha: Premnagar.
Construction of Two Laning with Hard Shoulder of Tara - Premnagar - Ramanujnagar Road Section fromExisting Chanaige Km 0.000 to Km 50.312 (Design Chainage from Km 0.000 to Km 50.242) in the State of Chhattisgarh on EPC Mode. Length : 50.242 Km Name of District: Surajpur. Vidhansabha: Premnagar.
TECHNICAL
Double Lane with Hard shoulder Major Bridge :
Numbers Nil
Locations - Minor Bridge.
Numbers 2 Nos
Locations at ch. 7+839-Box 6x4, ch. 43+924 Box 6x4 Culverts
Numbers :
HPC 1 Rowx1200-50nos, 2 Rowx1200-10 Nos, 3 Rowx1200-3= Total 63 Nos.
slab at ch. 0+399, 1+225,41+583, 42+400, 1x2.00m 43+450= Total 5 Nos
Box at ch. 3+863, 25+100 =Total 2 Nos. 1x5.00m
Numbers:
Locations Amount of Technical Sanction 13057.87 Lakhs
Numbers Nil
Locations - Minor Bridge.
Numbers 2 Nos
Locations at ch. 7+839-Box 6x4, ch. 43+924 Box 6x4 Culverts
Numbers :
HPC 1 Rowx1200-50nos, 2 Rowx1200-10 Nos, 3 Rowx1200-3= Total 63 Nos.
slab at ch. 0+399, 1+225,41+583, 42+400, 1x2.00m 43+450= Total 5 Nos
Box at ch. 3+863, 25+100 =Total 2 Nos. 1x5.00m
Numbers:
Locations Amount of Technical Sanction 13057.87 Lakhs